Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT:
ASX: DAL
27 October 2023
Quarterly Activities Report
For Period Ended 30 September 2023
_____________________________________________________________________________
Highlights
Lyons River in the Gascoyne Region of Western Australia – an emerging lithium and rare
element hotspot
Lithium
• Assessment of Lyons River Project wide lithium in soil geochemical data comprising 3,856
samples highlighted north-trending faults in the D5 Edmundian shear zones and the possible
flow of Li-rich melts into the fault compartments in the central part of Lyons River Project.
• Infill soil geochemistry defined several new lithium targets at View Hill prospect in the
Gascoyne Province of Western Australia.
• The View Hill targets have a peak value of 334 ppm Li2O and lie within a large pegmatite cluster
measuring 9km X 6km in the eastern part of Lyons River and remains open to the south, west
and east.
• Exploration is being fast tracked to complete rock chip sampling over View Hill and at other
lithium anomalies to define spodumene-bearing pegmatites with drill planning in progress.
Rare Earth Elements (REE)
• Two significant Rare Earth Element (REE) anomalies outlined at View Hill and 32 Mile Well
prospects in the Gascoyne region of Western Australia.
• REE anomalism at View Hill with peak value of 1,043 ppm TREO (Total Rare Earth Oxides) and
strike length of 2.2km coincides with large thorium high. REE anomalism at 32 Mile Well with
a peak value of 2,025 ppm TREO has a strike length of more than 3km.
• REE anomalies lie adjacent to a major NE-trending structural feature, compatible with
relationships seen at Kingfisher Mining’s Mick Well REE discovery. Anomalies could represent
hard rock or clay hosted REE mineralisation.
Namban
•
•
•
Maiden diamond drilling program over Dalaroo’s 100% owned Manning Prospect has
intersected copper sulphide mineralisation and gold mineralisation west of MI6’s Moora
Project along strike of the Mt Yule Trend.
The drilling further confirms mafic rocks (gabbroic dolerites) prospective for magmatic
intrusion hosted Ni-Cu-PGE-Au mineralisation at Manning, only 150km north of Perth in
Western Australia.
The diamond drill program at Manning was partly funded by the Exploration Incentive Scheme
grant awarded to Dalaroo by the Government of Western Australia.
Dalaroo Metals Ltd (ASX: DAL, “Dalaroo” or “Company”) is pleased to provide an update on its activities
during the September Quarter 2023.
Lyons River Project
Dalaroo’s Lyons River Project comprises a strategic (100% owned) land position of 740km2 within the
Proterozoic Mutherbukin Zone of the Gascoyne Province, Western Australia. Lyons River is prospective
for REE, lithium, vein/shear related gold and base metals (Pb-Zn-Ag) deposits (Figure 1).
Figure 1: Dalaroo Metals, Lyons River Project in the Gascoyne Province REE and lithium neighbouring companies
and prospects
2
Lithium Potential
The new lithium targets at Dalaroo’s View Hill prospect have been outlined by follow-up/infill soil
geochemistry, completed in August 2023 on a 200m X 100m pattern (first pass sampling was completed
on lines 1km X 100m). A total of 813 soil samples have been collected at View Hill. One of the lithium
targets (3km long and 0.5km) has a peak value of 334 ppm Li2O and is comparable to lithium anomalism
obtained by Dalaroo’s neighbours (Refer MI6 ASX Announcement dated 25 July 2023). Importantly, the
lithium targets lie within the large pegmatite cluster measuring 9km X 6km in the eastern part of the
project, where pegmatites up to 100m wide and 3km long have been mapped (Figure 2). The significant
lithium anomalism outlined to date remains open to the south, west and east (Figures 3 and 4).
Figure 2: Lyons River Project – Major shear zone/corridor active during the Edmundian Orogeny,
with potential for lithium bearing pegmatites.
Structural mapping within the Lyons River Project has identified several major shear zones, each over
30km long and 6km wide, that formed during the Neoproterozoic Edmundian Orogeny. This orogeny
was the fundamental driver of deformation along the nearby Ti Tree Shear Zone, and it was responsible
for the emplacement of spodumene pegmatites in the Yinnetharra District, which are now the focus of
Delta Lithium’s resource drilling activity.
3
View Hill
Figure 3: Structural domain map with north-south faults and significant lithium targets
outlined at View Hill Lyons River Project.
Pegmatites emplaced during the Edmundian Orogeny are associated with granite intrusions of the Thirty
Three Supersuite (TTS) and recent mapping has confirmed that intrusive rocks of the TTS were also
emplaced within shear zones at the Lyons River Project (Figure 2). The TTS intrusions comprise granite
stocks and granitic pegmatite (microcline-quartz-muscovite-tourmaline). Large pegmatite swarms have
been mapped in the central part of the project area, as well as in the east (View Hill) where they cover
an area of 9km X 6km. Rock chip sampling completed to date of outcropping pegmatites at View Hill has
confirmed whole rock geochemistry considered highly fertile for LCT-type pegmatites (Figure 2).
A pegmatite swarm that outcrops in the newly identified shear zone and across a 9km X 6km area has
returned anomalous rock chip values of 245 ppm Li2O, 1638 ppm Rb, 187 ppm Nb and 183 ppm Sn. Rock
chip sampling of pegmatites, west of View Hill in the central part of Lyons River Project, has returned
significant Ta2O5 and Nb values of 143 ppm and 328 ppm respectively with anomalous Rb of 904 ppm
(Refer DAL ASX Announcements from 1 December 2022 and 12 October 2023). This is indicative of highly
fractionated LCT pegmatites and supports the interpretation that the shear zone/corridor is fertile, with
potential for higher grade lithium at depth.
4
Photo 1 a: Thirty Three Supersuite pegmatites with (microcline-muscovite +/- tourmaline assemblage) and photo
1b dominated by microcline and muscovite mica “books”.
Figure 5: View Hill: lithium soil geochemistry showing main anomalous trends, open to the south, west and east.
5
Rare Earths
Two significant REE anomalies have been outlined at the View Hill and 32 Mile Well prospects. The REE
anomalism with a peak value of 1,043ppm TREO at Zone 1 has a strike length of 2.2km, average width
of 500m and coincides with a large NW trending thorium high identified in detailed radiometric imagery
data flown by the Company. The second REE anomaly with a peak value of 2,025 ppm TREO has a current
strike length of over 3km and an average width of 300m (Figure 6).
Figure 6: TREO results on radiometrics thorium/google image (note coincident large thorium and TREO anomaly
at View Hill prospect).
6
Importantly both REE anomalies lie adjacent to a major NE-trending structure, compatible with
relationships seen at Kingfisher Mining’s Mick Well REE discovery. The anomalies have no recorded
drilling and could therefore represent either potential hard rock or near surface clay hosted
mineralisation drill targets. A total 309 soil samples were collected over the greater View Hill and 32
Mile Well prospect areas as part of the follow up sampling program on lines 1km apart at 100m intervals
(Figure 2). First pass REE results at View Hill had returned values of up to 1043 ppm TREO reported
(Refer DAL ASX Announcement dated 4 April 2023).
Next Steps at Lyons River
Lithium Potential
Current phase of pegmatite rock-chip sampling and detailed field geological mapping to outline Libearing spodumene pegmatites within the 30km long northern shear zone is well underway, expected
to be completed by end of October 2023.
Assay results from rock chip sampling of the highly fertile for LCT-type pegmatites is expected to be
received during October 2023. The results from this sampling program will lead to drill target definition.
Exploration is being fast tracked to complete rock chip sampling over View Hill and at other lithium
anomalies with drill planning in progress. Drill testing will be undertaken once all approvals are in place.
REE Potential
Infill soil sampling over the View Hill and 32 Mile Well prospects which have strike lengths of 2.2km and
3km respectively will be completed on a 200m X 40m pattern. Rock chip sampling will be undertaken
over the REE anomalous zones. The results from the infill sampling is expected to delineate drill targets.
Namban Project
The Manning Prospect is located 150km north of Perth and 90km north of Chalice Mining’s world class
Julimar Ni-Cu-PGE Project (Figures 6 and 10). The drilling program was designed to test large Ni-CuPGE*+Au geochemical anomalies (Pd soil anomaly with a peak value of 28 ppb coincident with Cu peak
value of 605 ppm and Ni peak value of 206 ppm) covering an area of 2km X 0.5km that are coincident
with Induced Polarisation (IP) anomalies with high chargeability values of up to 40 mV/V.
The diamond drill program was partly funded by Dalaroo’s successful application in Round 26 of the
Exploration Incentive Scheme sponsored by the Government of Western Australia. The grant was for an
amount of up to $175,000, structured as a contribution towards 50% of direct drilling cost.
A diamond drilling programme of four holes (MNDD001 to MNDD004) totalling 828.9m was completed
at the Manning Prospect as part of Round 26, co-funded drilling grant (Figure 7). The holes ranged in
depth from 178.1m to 267.4m (Table 1).
7
Elevated copper, gold and silver assays up to 0.11% Cu, 0.61 g/t Au and 14.5 g/t Ag were intersected in
the drilling program (Table 2).
Host lithologies are interpreted as differentiated intrusive mafic rocks (gabbroic dolerites) believed to
be part of a larger (dismembered) intrusive mafic sill complex within a sequence of high-grade
metamorphic rocks (gneisses/granulites) that remains prospective for magmatic intrusion hosted Ni-CuPGE-Au mineralisation at Namban.
Two orientations of chlorite-sulphide veinlets/fractures trending subvertical north-west and north
north-west were logged in the holes. A steep NW plunge is inferred from the intersection of the vein
sets. The sulphide intersections comprising chalcopyrite-pyrite+/- pyrrhotite rich zones in MNDD004.
Pyrite-carbonate alteration was noted in fractured felsic dykes that are NNW trending and are coincident
with the regional copper and gold trend around the margins of the interpreted Julimar-Mt Yule Gravity
corridor depicted in Figure 6.
Table 1: Manning - Drill hole locations.
Hole Id
MNDD001
MNDD002
MNDD003
MNDD004
Easting
(GDA Z50)
410400
409250
410189
409890
Northing
(GDA Z50)
6610975
6610300
6611072
6611075
RL
(m)
290
290
290
290
Final/Depth
(m)
203.9
178.1
179.4
267.4
Azimuth
(Degrees)
266
090
090
065
Dip
(Degrees)
-65
-60
-60
-60
Table 2: Manning prospect - Significant assays
Hole Id
MNDD001
MNDD002
MNDD003
MNDD004
Incl.
+
From
(m)
0.00
173.0
To
(m)
0.50
174.0
Interval
(m)
0.5
1.0
Au g/t
Ag g/t
Cu ppm
NSR
0.61
NSR
NSR
14.5
NSR
NSR
NSR
NSR
NSR
NSR
749
1061
1044
21.4
22.25
0.85
21.4
21.70
0.30
21.95
22.25
0.30
NSR – denotes no significant result above 0.5 g/t Au, 10 g/t Ag or 0.05% Cu
8
Figure 6: Namban Project – Manning prospect: Contoured soil anomalies, diamond drill hole locations and
bedrock anomalies. Contours >5ppb Au contours in red; >75ppm Cu in green; >100ppm Ni in magenta; >5ppb Pt
in blue
9
Figure 7: Namban Project Location along the northern extent of the arcuate Julimar – Yule Corridor, truncated by
the Darling Fault (dark blue) to the west. Image is 1VD-RTP magnetics draped with Bouger Gravity
10
Next Steps at Namban – Manning
Given the significant size of the surface geochemical anomalism (Ni-Cu-PGE*+Au) outlined (measuring
2km X 0.5km) at the Manning Prospect and only four holes drilled using Dalaroo’s successful application
in Round 26 of the Exploration Incentive Scheme with a grant of $175,000, further exploration work is
warranted.
Future work at the Manning Prospect will include ground gravity surveys, which are expected to
complement and expand upon the existing geochemical and geophysical datasets which have helped to
delineate encouraging sulphide copper and gold mineralisation.
Gravity surveys will provide additional insight through mapping the local density variation and
potentially define deep seated intrusions or sources to the base metal mineralisation and differentiate
prospective mafic and gabbroic units from the more recent Proterozoic dolerite dykes which trend
through the project and provide targets for potential follow up drill programs.
Corporate
As at the date of this report, the Company has the following securities on issue:
Security Type
Number
Fully Paid Ordinary Shares
81,600,000
Unlisted Options - exercisable at $0.25 each, expiring 28 September 2025
8,000,000
Unlisted Options – exercisable at $0.25 each, expiring 28 September 2024
5,000,000
Unlisted Options – exercisable at $0.08 each, expiring 5 July 2025
13,800,000
On 27 July 2023 the Company received approval at a General Meeting of shareholders to complete
Tranche Two of the June 2023 capital raising, which resulted in the issue of 8,550,000 fully paid ordinary
shares in the capital of the Company (Shares) at an issue price of $0.05 per share and 11 million unlisted
options exercisable at $0.08 each, expiring 5 June 2025. Since the end of the September Quarter 2023,
the Company has conducted an additional placement of 5,800,000 Shares at an issue price $0.04 per share
and 2,800,000 free attaching options exercisable at $0.08 each, expiring 5 June 2025.
Listing Rule 5.3.4 Use of Funds
Dalaroo was admitted to trading on ASX on 28 September 2021. The September Quarter 2023 is included
in a period covered by a Use of Funds statement in a prospectus dated 26 August 2021 and lodged with
ASX under Listing Rule 1.1 condition 3. A comparison of the Company’s expenditure since listing against
the estimated Use of Funds statement is set out below as required under Listing Rule 5.3.4.
11
Expenditure Item
Estimate for the two years
after ASX Admission
($’000)
Actual Use of Funds
Variance
to 30 September
Under/(Over)
2023
($’000)
($’000)
Exploration – Namban Project
1,425
1,836
(411)
Exploration – Lyons River Project
1,775
2,317
(542)
Working Capital and Administration
1,673
2,035
(362)
Estimated expenses of the Offer
541
561
(20)
TOTAL
5,414
6,749
(1,335)
Financial Commentary
The Appendix 5B for the quarter ended 30 September 2023 provides an overview of the Company’s
financial activities. Exploration expenditure for the quarter was $431K. Corporate, staff costs and other
expenditure for the quarter was $278K. The total amount paid to Directors of the Company, their
associates and other related parties was $132K which includes salary and fees and rent paid to Borden
Holdings Pty Ltd (an entity associated with Mr David Quinlivan) for leasing the corporate offices.
The Company’s cash balance at the end of the quarter was $514K.
ENDS
For more Information:
Please visit our website for more information: www.dalaroometals.com.au
Harjinder Kehal, Managing Director on +61 400 044 890
Authorised for release to the ASX by the Board of Dalaroo Metals Ltd.
COMPETENT PERSON
The information in this report that relates to Exploration results is based on information compiled by
Dalaroo Metals Ltd and reviewed by Mr Harjinder Kehal who is the Managing Director of the Company
and is a Registered Practicing Geologist and Member of the AusIMM and AIG. Mr Kehal has sufficient
experience that is relevant to the style of mineralisation, the type of deposit under consideration and to
the activities undertaken to qualify as a Competent person as defined in the 2012 edition of the
“Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Kehal
consents to the inclusion in this report of the matters based on this information in the form and context
in which it appears.
12
FORWARD-LOOKING INFORMATION
This report may include forward-looking statements. Forward-looking statements include, but are not
limited to, statements concerning the planned exploration program and other statements that are not
historical facts. When used in this report, the words "could", "plan", "estimate", "expect", "intend",
"should" and similar expressions are forward-looking statements. Although Dalaroo believes that its
expectations reflected in these forward-looking statements are reasonable, such statements involve
risks and uncertainties and no assurance can be given that actual results will be consistent with these
forward-looking statements.
CAUTIONARY NOTE
The statements and information contained in this report are not investment or financial product advice
and are not intended to be used by persons in deciding to make an investment decision. In releasing this
report, Dalaroo has not considered the objectives, financial position or requirements of any particular
recipient. Accordingly, potential investors should obtain financial advice from a qualified financial
advisor prior to making an investment decision.
The identification of pegmatites in the mapping completed to date does not imply the presence of
lithium mineralisation. The presence of any lithium mineralisation will be determined by drilling and
laboratory analyses.
1
ASX Releases during the September Quarter 2023
Description
27 July 2023
Results of General Meeting
28 July 2023
Quarterly Activities Report/Appendix 5B Cash Flow Report – June Quarter 2023
2 August 2023
Heavy Rare Earths and Lithium potential expanded at Lyons River
3 August 2023
Ceasing to be a substantial holder
7 August 2023
Investor Presentation August 2023
7 August 2023
Application for quotation of securities - DAL
8 August 2023
Completion of Placement Notice Under Section 708A(5)(e)
8 August 2023
Notification regarding unquoted securities - DAL
8 August 2023
Change of Directors interest Notice X 3
8 August 2023
Change in substantial holding
16 August 2023
Change in substantial holding
30 August 2023
Copper & Gold mineralisation intersected at Manning Prospect
13 September 2023
Investor Presentation September 2023
20 September 2023
Securities Being Released from Escrow
28 September 2023
Lithium Potential Enhanced at Lyons River Project
28 September 2023
Annual Report to shareholders
28 September 2023
Appendix 4G & 2023 Corporate Governance Statement
28 September 2023
Application for quotation of securities - DAL
13
TENEMENT SCHEDULE AS AT 30 SEPTEMBER 2023
Interest held at
30 September 2023
Project Name
Location
Tenement Licence
Lyons River
WA
E09/1824
Lyons River
WA
E09/1825
100%
Lyons River
WA
E09/2098
100%
Lyons River
WA
E09/2102
100%
Lyons River
WA
E09/2304
100%
Lyons River
WA
E09/2305
100%
Lyons River
WA
E09/2312
100%
Lyons River
WA
E09/2713 (application)
100%
Namban
WA
E70/4694
100%
Namban
WA
E70/4928
100%
Namban
WA
E70/5702
100%
Namban
WA
E70/5494
100%
Namban
WA
E70/5502
100%
Namban
WA
E70/5604
100%
100%
Note: All the Tenement Licences are granted, apart from E09/2713
14
About the Lyons River Project
Lyons River Project is located approximately 1,100km north of Perth and approximately 220km to the
north-east of the coastal town of Carnarvon, Western Australia (Figure 8). It lies within the Mutherbukin
Zone of the Gascoyne Province, which is the deformed and high-grade metamorphic core zone of the
early Proterozioc Capricorn Orogen an emerging lithium and rare earth element hotspot.
The Project comprises approximately 740km2 of the Durlacher Super Suite and Halfway Gneiss,
transected by major NW-trending shear zones. This same stratigraphy and comparable structural setting
hosts significant REE deposits nearby to the north, at the Hastings Technology Metals Yangibana and
Dreadnought Resources Mangaroon projects, and to the south at Kingfisher Mining’s Mick Well Project
(Figure 8).
Figure 8: Lyons River Project location diagram
15
About the Namban Project
Namban Project comprises an under explored ground package totalling 437km2 located in the mid-north
part of the wheatbelt region, deemed by Dalaroo to be prospective for magmatic intrusion related NiCu-PGE deposits. The Company has a 100% controlling interest in the Namban Project, comprising six
tenements extending from the townships of Moora in the south to Three Springs in the north (Figure 9).
Figure 9: Namban Project tenements location map.
16
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
DALAROO METALS LTD
ABN
Quarter ended (“current quarter”)
23 648 476 699
30 September 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
Year to date
(3 months)
$A’000
-
-
(431)
(431)
(b) development
-
-
(c) production
-
-
(d) staff costs
(152)
(152)
(e) administration and corporate costs
(126)
(126)
(a) exploration & evaluation
1.3
Dividends received (see note 3)
-
-
1.4
Interest received
2
2
1.5
Interest and other costs of finance paid
-
-
1.6
Income taxes paid
-
-
1.7
Government grants and tax incentives
-
-
1.8
Other (provide details if material)
2
2
1.9
Net cash from / (used in) operating
activities
(703)
(703)
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) exploration & evaluation
-
-
(e) investments
-
-
(f)
-
-
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(3 months)
$A’000
Proceeds from the disposal of:
(a) entities
-
-
(b) tenements
-
-
(c) property, plant and equipment
-
-
(d) investments
-
-
(e) other non-current assets
-
-
2.3
Cash flows from loans to other entities
-
-
2.4
Dividends received (see note 3)
-
-
2.5
Other (provide details if material)
-
-
2.6
Net cash from / (used in) investing
activities
-
-
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
401
401
3.2
Proceeds from issue of convertible debt
securities
-
-
3.3
Proceeds from exercise of options
-
-
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(26)
(26)
3.5
Proceeds from borrowings
-
-
3.6
Repayment of borrowings
-
-
3.7
Transaction costs related to loans and
borrowings
-
-
3.8
Dividends paid
-
-
3.9
Other (provide details if material)
-
-
3.10
Net cash from / (used in) financing
activities
375
375
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
843
843
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(703)
(703)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
-
-
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
375
375
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(3 months)
$A’000
4.5
Effect of movement in exchange rates on
cash held
-
-
4.6
Cash and cash equivalents at end of
period
514
514
5.
Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1
Bank balances
5.2
Call deposits
514
843
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
5.5
Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
514
843
6.
Payments to related parties of the entity and their
associates
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
132
6.2
Aggregate amount of payments to related parties and their
associates included in item 2
-
Current quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1
Loan facilities
-
-
7.2
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
-
Page 3
3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
8.2
(Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(703)
8.4
Cash and cash equivalents at quarter end (item 4.6)
514
8.5
Unused finance facilities available at quarter end (item 7.5)
8.6
Total available funding (item 8.4 + item 8.5)
514
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
0.7
(703)
-
-
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Yes
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: Yes, the Company has conducted a capital raising via existing shareholders,
brokers and sophisticated and professional investors to ensure it has sufficient
capital to fund its future operations. The first tranche has been received in October
2023 while the second tranche will be received after the AGM. The directors of the
Company have indicated that they will contribute funds to support the capital
raising. The Company believes there is a high likelihood of continuing to raise the
capital required.
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Yes, by raising sufficient cash to support its current exploration programmes.
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
27 October 2023
Authorised by: The Board of Dalaroo Metals Ltd
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2
Share your feedback
Discover